Below is a scorecard that offers the current progress and status of the bunker renovation.  We began with the red nine and will transfer shortly to the blue nine.  All that is left to do on the red nine is to install the new sand in the bunkers.   The previous steps of edging, removing the old sand, adding gravel, spraying the polymer coating over the gravel have all been completed.  The continued rain days are limiting our ability to get heavier tractors and trailers onto the course to deliver the sand to the bunkers.  As soon as it dries we will continue with the sand work.

We will open the red nine as soon as the last bunker has sand installed.  Hopefully that will be the end of this week (October 20th.)

This is a partial amount of the new sand that will be placed in the renovated red and blue bunkers.
Red nine bunker renovation is now completed.  The reviews are very positive.

Red  Total #  Edged  New Gravel  Polymer  Sand 
Nine  Bunkers    Sod      
#1 4 4 4 4 4 4
#2 5 5 5 5 5 5
#3 4 4 4 4 4 4
#4 2 2 2 2 2 2
#5 4 4 4 4 4 4
#6 1 1 1 1 1 1
#7  1 1 1 1 1 1
#8  5 5 4 4 4 4
#9  6 6 6 6 6 6
32 100% 100% 100% 100% 100%