Red #4 bunker- The new sand
The red nine bunker renovation is complete and the project has shifted to the blue nine. The weather continues to impact the project to a degree. The contractor is continuing to work as long as the weather permits.
The two bunkers at the short game area will be renovated upon completion of the blue nine bunkers.
Below is a progress report on the blue nine bunkers as of December 18th.
Blue | Total # | Edged | Sod | Gravel | Polymer | Sand |
Nine | Bunkers | |||||
#1 | 3 | 3 | 3 | 3 | 2 | |
#2 | 4 | 4 | 4 | 4 | 3 | |
#3 | 5 | 5 | 5 | 5 | 5 | 4 |
#4 | 2 | 2 | 2 | 2 | 2 | 3 |
#5 | 3 | 3 | 3 | 3 | 3 | 2 |
#6 | 9 | 9 | 9 | 9 | 8 | 4 |
#7 | 4 | 4 | 4 | 4 | 4 | |
#8 | 4 | 4 | 4 | 4 | 4 | |
#9 | 5 | 5 | 5 | 5 | 5 | |
% | ||||||
Complete | 39 | 100% | 100% | 100% | 92% | 26 % |