The new vertical edges of the bunkers are shaped
The old sod is removed from around the bunker
The contaminated sand is removed from the bunkers
The drainage is checked for proper performance
New sod is added around the bunker
New gravel is added to the floor of the bunker
A polymer is sprayed on top of the gravel
Our staff checks the polymer application for proper polymer levels
The new sand is added to the bunkers
Sand depths are checked for proper depth
The new sand is compacted to firm the surface
The finished product